Wednesday, April 1, 2009

YES - We have moved in

Sorry for not updating for so long.. pretty flat out during and after the move...Fence, Driveway, Lights and some window coverings are in.. Landscaping planned for later this month...though there isn't much to do in the front as I have concreted almost 80% in the front with an entry and exit..built a new cross over as well..
Will update internal pics soon..

Saturday, February 21, 2009

Latest Pics - Feb 20th

Latest frontage pics... render colours still pending... but I kinda like those yellows which will go.


Pic taken from formal lounge towards entry

Kitchen ceaserstone benchtop installed.

Close up shot ceaserstone benchtop.. Paid extra for it to be rounded in the corners...much recommended.

ensuite n bathroom tiling

Laundry Master ensuite shower

Master ensuite


Bath Shower

Bathroom

More feature colour pics (as requested by a fan)







Thursday, February 5, 2009

Wall Colours

Media Room with Feature Wall (Vintage Plum)



Lounge Feature Wall (Wild Fig)


Main entry colours (Main Interior walls – Chalk Beige; Doors and Skirtings – Chalk Dust)
From Lounge towards main entry
Family Room with Feature Wall (Turkish Bread)

Lounge - Dining Colours

Wednesday, January 21, 2009

Week-19 to 23 update

It has been a while we have posted an update..due to obvious reasons... there hasn't been much work happening over the Christmas period. There was no work at all for 2 weeks after Christmas but it has slowly started picking up after the first week of new year.


The internal paint work is all complete now... will post a few pics on that soon..


Garage work will be completed by next week and the tiling will also start during next week...
Two other major works include electrical and plumbing fittings..

The rendering has started yesterday and will take about a week to finish... YES .. it is all happening and hopefully we should get the keys in early March (as per S/S) but he will confirm after tiling is complete.

A few pics with half rendered front (& guys working on it :) and also find the new front doors..



Saturday, December 13, 2008

Fixing almost complete (Week-18)

Went to the house yesterday and was quite surprised to find the carpenter working on the weekend (with heavy rain outside)...He was fixing the BIRs and skirting...Kitchen, ensuite and remaining cabinets are all fixed during the week...so not long before the Fixing stage is complete. Project seems to be on schedule and maybe even delivered prior to scheduled date...will have to ask Supervisor on Tuesday about the dates...
Remaining major work:
- Painting
- Garage frames & roof
- Front Rendering
- Electrical fittings
- Plumbing finishing & taps etc
- Tiling
- Mirrors and Shower screens

Kitchen (Above & below) - Burnished wood cabinets below bench top and oyster linea overhead cupboards...stone benchtop still to be installed...Pantry door in the middle in below pic.
Ensuite - Oyster linea for the whole lot...


Decorative columns..